00:12 106-year-old building
00:30 Weight on the floor was so heavy it did something to the floor
00:55 We're going to cut and repair it
01:20 Wanting to use 16' boards
02:10 100 years ago a one by was one inch
02:40 Not near as much room under as he thought
03:45 Floor is bowing because the 4x4s are in the wrong place

🙏 Subscribe, 👍, it helps a lot!!
➤❓/ 💬: ask@straightarrowrepair.com
➤ Follow https://straightarrowrepair.com/pipf

➤➤I get a little for the channel-no charge for you if you use the links:
➤➤Shop Amazon https://amzn.to/3CxD1T4
➤➤Tool lists & recommended products🧰 https://straightarrowrepair.com/0lvf

➤➤Services We use
➤➤MORNINGFA·ME https://morningfa.me/invite/StraightArrowRepair
➤➤A2 Hosting http://www.a2hosting.com/refer/140244
➤➤Tubebuddy https://www.tubebuddy.com/StraightArrowRepair
➤➤Apsumo http://fbuy.me/v/philbridges
➤➤VidIQ: https://vidiq.com/straightarrowrepair

#floorsupport, #floorrepair, #woodenfloor

Transcript:
Hello, here we are with another problem that we're trying to take care of. This is a 106 year old building. First use was the World War One draft board, 1914. Anyway, the weight on this wall was so heavy that it did something to the floor, if you notice, the floor’s got a pretty good size hump, say three or four inches goes all the way down here, pretty thick floor, and we're going to cut over here and make a doorway that you can get rolling in and out.

Because there's no way to get under here. We'll see what we got. So we'll mark out the doorway area and and we'll cut a door that will fit. I need to make sure I can get pretty good sized boards say, 16 foot. So that's why I chose to be right here. This is 1012, so I can almost hit 16 foot.

I go all the way to right here. I want like a four foot area. So, we’re going to mark maybe from this are here to straight you go about a foot and then go four foot. And that way we get longer boards, beams in here. So first thing we do is measure the width of this walkway, which is quite thick. It is straight up one and an eighth inches.

So a one inch then, was one inch and more. Let’s see how far down, it doesn't look that's very far down, not very far down to dirt. Oh, I was thinking there's going to be a lot more room. Well, now we can tell where the floors joists are. And go from there.

So what we determined was the floor joists and moving, not moving, the floor covering, which is actually an inch and an eighth thick is moving because these 4x4s, they put them in with no idea that they needed to sit on top of the floor joints. So all the weight sitting in between the floor joists is here, and it's right here. And it was kind of...

The floor joists are not particularly running square and there's no support through the middle here. So what we're going to do is cut the floor out here to here. We're going to support underneath that side because we can reach it and we're going to put support down through the middle and we'll probably put some support on this side. And then I'll talk to the owner and see if he's okay with me moving the post where it sits on the floor joists.

Getting another post, and putting it there. That would probably support a lot of weight.