If (WP) budgeted cost of work completed = 350.
3 years ago
29.6K
(WP) actual cost of work completed = 400 and (WS) budgeted cost of planned work = 325, what is the (SPI) schedule performance indicator. 0.8130.8751.0771.14324. The total estimated cost of the project is $20,000 and the allowable range is $0000-$250,000, which category of cost estimate does this fall into. Informal order of magnitude defined budget
Loading comments...
-
LIVE
Mally_Mouse
10 hours ago📣Telescreen Talks - LIVE!
135 watching -
LIVE
Quite Frankly
6 hours agoAggressive Texting, Practice Citizenship Test, Fed vs Fed | 10/29/25
459 watching -
LIVE
Blabs Games
1 hour agoLet's Get Funky - Jurassic World Evolution 3 Stream #2
89 watching -
LIVE
Putther
40 minutes ago🔴BILLY ANDERSON RETURNS!
33 watching -
LIVE
The Mike Schwartz Show
2 hours agoTHE MIKE SCHWARTZ SHOW Evening Edition 10-29-2025
3,431 watching -
LIVE
SavageJayGatsby
3 hours ago📣Telescreen Talks - LIVE!
31 watching -
LIVE
Reidboyy
6 hours agoI found the BEST Controller Settings for RedSec
15 watching -
LIVE
Phyxicx
3 hours agoStuff and Things - 10/29/2025
20 watching -
LIVE
Rah_Gaming
1 hour agoEnd Of The Resident Evil Marathon Tonight!
7 watching -
LIVE
Nikko Ortiz
2 hours agoREALISTIC BATTLEFIELD SIMULATOR... |Rumble Live
135 watching