Guy91

Guy91

    Management
    0:09
    the budgeted costs and the required quality.
    0:08
    Overview Successful project management is about
    0:08
    Use the current deviation as if it were a typical
    0:08
    (actual expenditure + budget for remaining items
    0:08
    will not occur again. (where BAC-EV is the
    0:08
    not suitable 2) Equation 2 EAC = AC + BAC-EV
    0:08
    ⊙ Past implementation shows that the original
    0:09
    (behind schedule) Project performance assessment methods deviation analysis
    0:15
    in the completed work up to a certain point.
    0:08
    EV (Earned Value) t
    0:08
    components Cost Change Request
    0:09
    Requested Changes Recommended Corrective
    0:10
    Measurement Forecasting Techniques Project Performance Assessment Project Management
    0:08
    Project's Funding Requirements Cost Performance
    0:08
    Prevent problems with project scope
    0:09