The following table contains information related to the major activities of a given project
a) Draw the project network
b) Find the critical path
c) Find the project completion time

Activity Immediate Predecessor Activity Duration (weeks)
A --------- 8
B A 5
C A 7
D C 2
E --------- 3
F E 6
G -------- 1
H G 2
I B, D 10
J F, I 8
K H 17