CE Board HGE Problem 26 (Hydraulics and Geotechnical Engineering) - CE Nov 2023

1 month ago
3

A clay layer 5 m. thick rests beneath a deposit of submerged sand 8 m. thick. The top of the sand is located 3 m. below the surface of a body of water. The saturated unit weight of the sand is 25 kN/m^3 , and the clay is 20 kN/m^3
a. evaluate the total vertical pressure at mid-height of the clay layer
b. evaluate the pore water pressure at mid-height of the clay layer
c. obtain the intergranular stress or effective stress at mid-height of the clay
-
CE Board HGE Problem 27 (Hydraulics and Geotechnical Engineering) - CE Nov 2023
-
paki pindot po sa "LIKE" button mga Engr.
and click SUBSCRIBE na rin po if hindi pa po kayo naka "SUBSCRIBE"

Maraming salamat po sa inyo mga Engineers and Future Engineers.
mabuhay po kayong lahat.
-
FB Page - https://www.facebook.com/MrComputerCiviLEngineer
Tiktok - https://www.tiktok.com/@SolUsmanJr
-------------
CREDIT:
-------------
Soundtrack:
Ace Attorney Dual Destinies - Apollo Justice (I'm fine)
Ace Attorney Spirit of Justice (Credit Theme)

Avatar:
SuperME Cartoon Avatar Maker (mobile app)

Reference:
"Licensure Exams for Civil Engineering" by BESAVILLA
"CE Reference for Licensure Examination" by GILLESANIA
-
#civilengineeringlicensureexam
#solusmanjr
#ceboardexam

Loading comments...