Guidelines on Monitoring Rating Index مانیٹرنگ ریٹنگ انڈیکس پر رہنمائی

1 year ago
6

Guidelines on Monitoring Rating Index
RATING INDEX FOR MONITORING
Sr. No Phase Criteria Maximum Point Points Obtained
P1.1 Planning Feasibility Study (with respect to threshold of cost of Project)
i Yes 5
ii No 0 0
P1.2 Stakeholders' Involvement in the preparation of PC-I
i Yes 5 5
ii No 0
P1.3 Baseline Data in PC-I
i Yes 5
ii No 0 0
P1.4 Scope Commensurate with Objectives
i Completely matched 5 5
ii Partially matched 3
iii Do Not Match 0
P1.5 Result-Based Monitoring Framework
i Yes 5
ii No 0 0
P1.6 Project Justification/ Need's Assessment
i Provided 5 5
ii Not Provided 0
Points Obtained of Planning = 15
A Weightage of P1 Indicators ((Points Obtained of Planning/30) x 100) *0.2= 10
P2.1 Execution Formulation of Project Team and Organization (PMU, PIU, PSU etc.)
i Formulated 5 N/A
ii Not Formulated 0

P2.2 Revisions of PC-I
i No Revision 10
ii One Revision 7
iii Two Revision 5 5
iv Three or more Revision 2
P2.3 Availability of Documents w.r.t (Hiring, Procurement, Training, Tenders & Bidding etc.)
i Provided 10
ii Partially Provided 5 5
iii Not Provided 0
P2.4 Internal Monitoring conducted by Department
i Yes 5
ii No 0 0
Points Obtained of Execution= 10
B Weightage of P2 Indicators ((Points Obtained of Execution/25) x 100) *0.3= 12
P3.1 Performance % Difference of Planned & Physical Progress
i lesser than 10% 10
ii in between 10% to 20% 5
iii Greater than 20% 2 2
P3.2 Data Availability & Response of Project Authorities
i Provided 10
ii Partially Provided 5 5
iii Not Provided 0
P3.3 Availability of Quality Control Data
i Provided 10
ii Partially Provided 5
iii Not Provided 0 0
Points Obtained of Performance= 7
C Weightage of P3 Indicators ((Points Obtained of Performance/ 30) x 100) *0.5= 12
Planning 20%, Execution 30%, Performance 50%

Total (A+B+C) 34

Overall Project Grading Above 70 Within Defined Limits Green
35-70 Need Consideration Yellow
Below 35 Critical Red