If (WP) budgeted cost of work completed = 350.

2 years ago
1

(WP) actual cost of work completed = 400 and (WS) budgeted cost of planned work = 325, what is the (SPI) schedule performance indicator. 0.8130.8751.0771.14324. The total estimated cost of the project is $20,000 and the allowable range is $0000-$250,000, which category of cost estimate does this fall into. Informal order of magnitude defined budget