If (WP) budgeted cost of work completed = 350.
Repost
2 years ago
1
(WP) actual cost of work completed = 400 and (WS) budgeted cost of planned work = 325, what is the (SPI) schedule performance indicator. 0.8130.8751.0771.14324. The total estimated cost of the project is $20,000 and the allowable range is $0000-$250,000, which category of cost estimate does this fall into. Informal order of magnitude defined budget
Loading comments...
-
1:31:18
Redacted News
8 hours agoEMERGENCY! NATO AND CIA ASSASSINATE TOP RUSSIAN GENERAL, PUTIN VOWS IMMEDIATE RETALIATION | Redacted
213K405 -
56:45
VSiNLive
7 hours ago $5.09 earnedFollow the Money with Mitch Moss & Pauly Howard | Hour 1
68.1K2 -
52:44
Candace Show Podcast
7 hours agoMy Conversation with Only Fans Model Lilly Phillips | Candace Ep 122
86K316 -
LIVE
tacetmort3m
7 hours ago🔴 LIVE - RELIC HUNTING CONTINUES - INDIANA JONES AND THE GREAT CIRCLE - PART 5
183 watching -
26:52
Silver Dragons
6 hours agoCoin Appraisal GONE WRONG - Can I Finally Fool the Coin Experts?
32.6K2 -
UPCOMING
Bare Knuckle Fighting Championship
12 hours agoBKFC on DAZN HOLLYWOOD WARREN vs RICHMAN WEIGH IN
23.5K -
6:49:16
StoneMountain64
10 hours agoNew PISTOL meta is here?
34.9K1 -
20:58
Goose Pimples
12 hours ago7 Ghost Videos SO SCARY You’ll Want a Priest on Speed Dial
19.8K3 -
2:24:59
The Nerd Realm
10 hours ago $2.80 earnedHollow Knight Voidheart Edition #09 | Nerd Realm Playthrough
36.2K2 -
1:21:14
Awaken With JP
11 hours agoDrones are for Dummies - LIES Ep 70
119K58