⊙ Past implementation shows
1 year ago
1
that the original estimate is completely out of date
⊙ Conditions change that the original estimate is not suitable 2) Equation 2: EAC = AC + BAC-EV (actual expenditure + budgeted BAC-EV for the remaining work) Application: The current deviation is considered exceptional and a similar deviation will not occur again. (where BAC-EV is the remaining budget3) Equation 3: EAC = AC + (BAC-EV)/CPI
Loading comments...
-
11:48
Anti-Disinfo League
1 year agoOLD WORLD TECHNIQUES THAT CANNOT BE DUPLICATED
1271 -
0:11
gastonnsovitz4oik
1 year agoEV (Earned Value) the budgeted value of work actually completed
14.1K -
0:15
Keele01
1 year agoimplementation information
2.82K -
0:27
ccproxeijoo
1 year ago $32.56 earnedMulti-programme analysis is used in
15K -
1:59
WXYZ
4 years agoKnowing the differences between estimates and contracts
17 -
3:39
WFTX
3 years agoNew method being used to preserve the past
26 -
5:15
One For Israel
10 months agoI stopped looking at the problems and became part of the solution!
17 -
2:28
MRDeVinney
11 months agoCalculation in Statism | Among the Finest Inventions of the Human Mind
-
12:00
Chutzpah
1 year agoOverworked - 7 Solutions to consider
21 -
0:29
ChresJore
1 year agoPlan implementation control close out
17.7K