Characteristics: light and fast, can make up for slow speed, and strong attack in rainy days
3 years ago
24.8K
Senior management requires the project to be completed two months ahead of schedule.
There is no change to the project scope and the cost must not exceed the budget. In this case, the most effective way to compress the schedule is to: catch up on work and follow up quickly with overtime to reduce task estimates 47. The process of revising the schedule based on the actual resources available is called resource: allocation. Adding. Scheduling. 48. The total float time for an activity on the critical path is
Loading comments...
-
5:26:11
cosmicvandenim
7 hours agoCOSMIC VAN DENIM | SEX APPEAL & HORROR
5.02K9 -
LIVE
DoldrumDan
3 hours agoFINISHING SEKIRO - DEPTH 5 TOP RANKED - DAY 50 NEW LIFE
50 watching -
23:40
MYLUNCHBREAK CHANNEL PAGE
1 day agoWe Want the Blueprints
54K15 -
LIVE
PenguinSteve
4 hours agoLIVE! Penguin to the Battlefield (6)
54 watching -
1:08:20
The Quartering
5 hours agoMTG Quits, Indian X Meltdown & FBI Caught Lying Again About Trump Assassin
131K71 -
1:01:33
Jeff Ahern
6 hours ago $10.15 earnedThe Saturday Show with Jeff Ahern
43.1K23 -
18:08
Professor Nez
6 hours ago🚨HOLY CRAP: Members of Congress Call for Military INSURRECTION!
106K96 -
4:14:26
Grant Cardone
9 hours agoHow to Buy Real Estate With NO Money Down (LIVE Training With Grant Cardone)
106K8 -
1:56:11
AlaskanBallistics
16 hours ago $5.65 earnedShooting the WhisperStrike WT30 Live!
22.7K6 -
19:53
MetatronHistory
23 hours agoRome VS Greece - Ultimate Clash of Civilizations Explained
62K17