If (WP) budgeted cost of work completed = 350. (WP) actual cost of work completed

2 years ago
10.9K

400 and (WS) budgeted cost of planned work = 325 what is the (SPI) schedule performance indicator. 0.8130.8751.0771.14324. The total estimated cost of the project is $20