46. Senior management re

2 years ago
31

re is no change in the scope of the project and the cost shall not exceed the budget. In this case, the most effective way to compress the schedule is to speed up the work, follow up the overtime work and reduce the task estimate. 47. The process of revising the schedule based on the actually available resources is called resource: allocation. Increase. Arrangement. Balance. 48. The total floating time of an activity on the critical path